Bid Opening Date | Contract Number
| |
Wednesday, October 15, 2014 at 2:00 p.m. at the El Dorado County Board Clerk's Office in Placerville. | PW 14-31068 | Francisco Drive Right-Turn Pocket Project -
Notice to Bidders, September 17, 2014, 10:00 a.m.
-
Project Plans,
September 17, 2014, 10:00 a.m.
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File,
September 23, 2014, 6:00 p.m.
-
List of Planholders,
October 9, 2014, 8:00 a.m.
-
Pre-bid Meeting Attendees,
October 9, 2014, 8:00 a.m.
-
Response to Bidders' Inquiries No. 1,
October 9, 2014, 8:00 a.m.
-
Addendum No. 1,
October 9, 2014, 8:00 a.m.
-
Response to Bidders' Inquiries No. 2,
October 10, 2014, 4:00 p.m.
-
Bid Summary,
October 16, 2014, 12:00 p.m.
- This contract was awarded to JD Pasquetti Engineering, Inc.
Supplemental Project Information |
Monday, September 8, 2014 at 2:00 p.m. at the El Dorado County Board Clerk's Office in Placerville. | PW 14-31074 |
Latrobe Road Gabion Wall Retrofit Project
Supplemental Project Information,
August 21, 2014, 12:00 p.m. -
List of Planholders,
September 4, 2014, 2:00 p.m.
-
Pre-bid Meeting Attendees,
August 28, 2014, 3:00 p.m.
-
Addendum No. 1,
August 28, 2014, 3:00 p.m.
-
Response to Bidders' Inquiries No. 1,
August 28, 2014, 3:00 p.m.
-
Addendum No. 2,
September 3, 2014, 3:00 p.m.
-
Response to Bidders' Inquiries No. 2,
September 4, 2014, 2:00 p.m.
-
Bid Summary,
September 9, 2014, 6:00 p.m.
- This contract was awarded to Advanced Geotechniques, Inc.
|
Monday, August 18, 2014 at 2 p.m. at Transportation's Tahoe Engineering office at 924 B Emerald Bay Road | PW 11-30593 |
Sawmill 2B Bike Path and Erosion Control Project -
Notice to Bidders,
July 18, 2014, 2:00 p.m.
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File,
July 24, 2014, 3:30 p.m.
-
Addendum No. 1,
July 25, 2014, 9:30 a.m.
-
List of Planholders,
August 6, 2014, 10:30 a.m.
-
Addendum No. 2,
August 5, 2014, 10:30 a.m.
-
Response to Bidders' Inquiries No. 1,
August 12, 2014, 9:30 a.m.
-
Addendum No. 3,
August 14, 2014, 10:30 a.m.
-
Pre-Bid Meeting Attendees,
August 14, 2014, 1:30 p.m
-
Bid Summary,
August 18, 2014, 3:30 p.m
- The contract was awarded to RaPiD Construction, Inc. dba Rapid General Engineering
Supplemental Project Information |
Thursday August 7, 2014 at 2 p.m. at Transportation's Tahoe Engineering office at 924 B Emerald Bay Road | PW 14-31060 |
Forest View Water Quality Project -
Notice to Bidders,
July 22, 2014, 9:00 a.m.
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File,
July 25, 2014, 10:00 a.m.
-
Addendum No. 1,
July 25, 2014, 10:30 a.m
-
List of Planholders,
August 7, 2014, 1:30 p.m.
-
Pre-Bid Meeting Attendees,
August 4, 2014, 2:30 p.m
-
Bid Summary,
August 7, 2014, 4:00 p.m.
- The contract was awarded to Thomas Haen Company, Inc.
|
Friday, August 1, 2014 at 2 p.m. at Transportation's Tahoe Engineering office at 924 B Emerald Bay Road | PW 13-30701 |
CSA 5 Upper Area Erosion Control Project -
Notice to Bidders,
July 18, 2014, 1:00 p.m
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File,
July 24, 2014, 10:00 a.m
-
List of Planholders,
July 31, 2014, 10:30 a.m
-
Pre-Bid Meeting Attendees,
July 24, 2014, 5:00 p.m
-
Response to Bidders' Inquiries No. 1,
July 24, 2014, 5:00 p.m
-
Addendum No. 1,
July 25, 2014, 9:30 a.m
-
Response to Bidders' Inquiries No. 2,
July 31, 2014, 5:30 p.m
-
Bid Summary, August 11, 2014, 3:00 p.m
- The contract was awarded to Thomas Haen Company, Inc.
|
Monday, July 28, 2014 at 2 p.m. at Transportation's Tahoe Engineering office at 924 B Emerald Bay Road | PW 12-30672 |
Lake Tahoe Blvd Enhancement Project -
Notice to Bidders,
June 26, 2014, 5:00 p.m.
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File,
July 24, 2014, 3:30 p.m.
-
List of Planholders,
July 25, 2014, 3:00 p.m.
-
Pre-Bid Meeting Attendees,
July 17, 2014, 3:00 p.m.
-
Response to Bidders' Inquiries No. 1,
July 18, 2014, 5:00 p.m.
-
Response to Bidders' Inquiries No. 2,
July 22, 2014, 12:00 p.m.
-
Addendum No. 1,
July 23, 2014, 8:00 a.m.
-
Addendum No. 2,
July 23, 2014, 12:30 p.m.
-
Response to Bidders' Inquiries No. 3,
July 23, 2014, 2:30 p.m.
-
Response to Bidders' Inquiries No. 4,
July 24, 2014, 4:00 p.m.
-
Bid Summary,
July 28, 2014, 4:00 p.m.
- The Contract was awarded to V&C Construction, Inc.
|
Monday, July 14, 2014 at 2 p.m. at Transportation's Tahoe Engineering office at 924 B Emerald Bay Road | PW 13-30700 |
Golden Bear Erosion Control Project -
Notice to Bidders,
June 23, 2014, 5:00 p.m.
-
List of Planholders,
July 10, 2014, 6:00 p.m.
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File, July 2, 2014, 6:00 p.m.
-
Pre-Bid Meeting Attendees July 8, 2014, 8:00 a.m.
-
Response to Bidders' Inquiries No.1 July 8, 2014, 11:00 a.m.
-
Response to Bidders' Inquiries No.2 July 10, 2014, 6:00 p.m.
-
Response to Bidders' Inquiries No.3 July 14, 2014, 11:00 a.m.
-
Bid Summary July 15, 2014, 2:00 p.m.
-
The contract was awarded to Thomas Haen Company, Inc.
|
Friday, February 28, 2014 at 2:00 p.m. | PW 11-30628 |
Northside School Class I Bike Path Project Phases 1 and 2 (2 Plan sets and 1 Contract Documents Book) Supplemental Project Information -
Project Cross Sections . February 25, 2014, 10:00 a.m.
- Informational Handout
-
Final Geotechnical Report, Northside School Class I Bike Path Project, El Dorado County, CA by Blackburn Consulting dated April 16, 2013,
January 24, 2014, 5:00 p.m.
-
Revised Standard Plans,
January 24, 2014, 5:00 p.m.
-
Technical Memorandum for Naturally Occurring Asbestos Testing by County of El Dorado Environmental Management Division dated April 10, 2013,
January 24, 2014, 5:00 p.m.
-
Caltrans As-built Plans for Knickerbocker Creek Culvert,
February 14, 2014,11:00 a.m.
-
Project Plans,
January 24, 2014, 5:00 p.m.
-
List of Planholders, February 25, 2014, 10:00 a.m.
-
Builders' Exchanges and Trade Journals with Plans and Specifications on File,
February 5, 2014, 6:00 p.m.
-
Pre-Bid Meeting Attendees,
February 14, 2014, 11:00 a.m.
-
Addendum No. 1,
February 14, 2014, 11:00 a.m.
-
Response to Bidders' Inquiries No.1,
February 14, 2014, 11:00 a.m.
-
Response to Bidders' Inquires No. 2,
February 20, 2014 12:00 p.m.
-
Addendum No. 2, February 25, 2014, 10:00 a.m.
-
Response to Bidders' Inquiries No. 3, February 25, 2014, 10:00 a.m.
-
Response to Bidders' Inquiries No. 4, February 27, 2014, 5:00 p.m.
-
Bid Summary, March 1, 2014, 3:00 p.m.
- The Contract was awarded to Sierra Nevada Construction, Inc.
|
Tuesday, January 21, 2014 at 2:00 p.m. at Transportation's office 2850 Fairlane Court | PW 11-30614 |
Class II Bike Lane on Cameron Park Drive from Palmer Drive to Hacienda Road (re-bid with revised scope of work) -
Notice to Bidders,
January 6, 2014, 6:00 p.m.
-
List of Planholders,
January 15, 2014, 7:00 p.m.
-
Pre-bid Meeting Attendee List, January 14, 2014, 6:00 p.m.
-
Response to Bidders' Inquiries No. 1 ,
January 14, 2014, 6:00 p.m.
-
Response to Bidders' Inquiries No. 2 ,
January 14, 2014, 6:00 p.m.
-
Bid Summary,
January 21, 2014, 4:00 p.m.
- The Contract was awarded to Sierra Nevada Construction, Inc.
|