General Contact Number: (530) 621-5567

Air Quality Management District

Fee Schedule


Click here to print


Air Quality Management District Fee Schedule for July 1, 2023 - June 30, 2024



Program Element
 Description
Fixed Fee
Unit Fee
0841Aggregate Plants$       2,563
$           -
0842Asphalt Batch Plants$       4,667
$           -
0970Boilers, Furnaces, Process Heaters, Ovens... <5 MM BTU/hr$          601
$           -
0971Boilers, Furnaces, Process Heaters, Ovens... 5-24 MM BTU/hr$          764
$           -
0972
Boilers, Furnaces, Process Heaters, Ovens... =>25 MM BTU/hr (Per BTU)$           -$       34.59
0891Bulk Plants <40,000 gallons$       1,279
$           -
0892Bulk Plants =>40,000 gallons
$       2,100
$           -
0957Gas Flares$          601
$           -
0958Incinerators <40 square feet$          601
$           -
0959Incinerators =>40 square feet$          764
$           -
0963Internal Combustion Engines for Backup Power <250 hp$          454
$           -
0964Internal Combustion Engines for Backup Power =>250 hp$          572
$           -
0849Landfills$       3,466
$           -
0980Material Handling and Collection Systems$          660
$           -
0990Miscellaneous Equipment$          572
$           -
0862Plating Lines$          449
$           -
0965Prime Power Internal Combustion Engines <500 hp$          815
$           -
0966Prime Power Internal Combustion Engines =>500 hp (per hp)$           -$         1.67
0857Remediation Systems$       1,881
$           -
0830Source Test Observation and Report Preparation (hourly rate)$           -$          172
0954Surface Coating Operations <520 pounds/year$          572
$           -
0955Surface Coating Operations =>520 pounds/year$          829
$           -
0982Vapor Recovery Systems, Phase One$          383
$           -
0984Vapor Recovery Systems, Phase Two$       1,279
$           -
1004Emissions of Carbon Monoxide CO (per ton)$           -$       13.80
1030Emissions of VOC, SOx, NOx, TSP (per ton)$           -$       82.48
0907Hot Spots Emissions =>10 tons (per ton passed through to State)$           -$       12.91
0907BHot Spots Emissions =>10 tons (per ton to AQMD)$           -$       17.39
0906Hot Spots Emissions <10 tons, flat rate$          100$           -
0951Asbestos Dust Mitigation Plan (base fee plus per acre fee)$          514
$       34.59
0882Authority to Construct Application$          466
$           -
0899Change of Ownership (base fee plus annual permit fees)$          122
$           -
0890Duplicate Permits$       33.26
$           -
0942Filing Fee$          122
$           -
0927Fugitive Dust Plans$          163
$           -
0952Geologic Evaluations$          686
$           -
0895Hourly Rate for AQMD staff time$          172
$          172
0944Processing Fee (= 2 hours)$          344
$           -
0912Hearing Board Variance CO Emissions (per pound)$           -$         0.13
0909Hearing Board Variance NOx Emissions (per pound)$           -$         9.23
0911Hearing Board Variance PM10 Emissions (per pound)$           -$         9.00
0910Hearing Board Variance SOx Emissions (per pound)$           -$         3.00
0908Hearing Board Variance VOC Emissions (per pound)$           -$       10.00
 Hearing Board Filing Fee$          277
$           -
 Hearing Board Filing Fee Interim or Emergency Variance$            72
$           -